A table of the stages a federal information collection goes through before it can be fielded, with the section of 5 CFR 1320 that governs each and its statutory clock. It runs from the 60-day Federal Register notice and the 30-day notice on submission to OMB's decision, the three-year approval limit and the narrow 90-day emergency route. Use it to plan a government research schedule. Koji can run the cleared instrument as AI-moderated interviews once approval is in place.
Where this appears
What's in this reference table
| Stage | Governing section | Statutory clock |
|---|---|---|
| First Federal Register notice | 5 CFR 1320.8(d)(1) | 60 days of public comment |
| Second notice on submission to OMB | 5 CFR 1320.10(a) | 30 days of comment to OMB |
| OMB decision | 5 CFR 1320.10(b) | Up to 60 days from the later of receipt or publication |
| Approval lifetime | 5 CFR 1320.10(b) | Maximum of three years |
| Emergency processing | 5 CFR 1320.13(f) | Control number valid a maximum of 90 days |
Use this image
Free to use in your docs, decks and posts under CC BY 4.0, as long as you credit Koji with a link to this page. To embed it, paste this into your page:
html
<a href="https://www.koji.so/visuals/omb-pra-clearance-timeline-stages"><img src="https://www.koji.so/visuals/omb-pra-clearance-timeline-stages/omb-pra-clearance-timeline-stages.png" alt="Table of the OMB clearance stages under the Paperwork Reduction Act: a 60-day notice, a 30-day notice, up to 60 days for OMB and a three-year approval limit." width="1200" height="748" /></a>
<p>Source: <a href="https://www.koji.so/visuals/omb-pra-clearance-timeline-stages">OMB clearance timeline under the Paperwork Reduction Act</a>, Koji</p>